How much of India's wind arrives after dark?
Half of it. Over the last twelve months 50% of India's wind power came between 7 pm and 6 am, and almost none of its solar. But wind is a monsoon source. On 57 evenings, nearly all between November and March, the whole fleet gave under 5 GW at the hour demand was highest.
Half of it
Solar stops at sunset. Wind does not. Over the twelve months to 31 October 2026, India's wind turbines made 279 gigawatt-hours (GWh) of electricity on the average day.[1] Half of it, 50.2%, came between 7 pm and 6 am.
Those 11 hours are 45.8% of the clock, so wind leans a little toward the night. Solar made 0.2% of its electricity in the same hours. After dark, wind supplied 6.3% of India's power. Across the whole day it supplied 5.5%.
Half is the answer for the year. It hides the two things a grid has to plan for: which months the wind blows in, and what it gives at the one hour each evening when India uses the most power. We count 7 pm to 6 am as after dark, as in our first piece on the evening.
The months differ far more than the hours
Average wind generation in each hour of the day, month by month, November 2025 to October 2026. Fuller colour is more wind. At the right, gigawatt-hours on the average day
GWh a day
Read a row across and the colour shifts by a shade or two. Read a column down and it goes from almost nothing to full. July 2026 made 584 GWh a day. November 2025 made 136, less than a quarter of that.
Across the year the fleet ran at an average of 11.6 gigawatts (GW). On 31 October 2026 it was a 59.5 GW fleet.[2] So the turbines gave about a fifth of what their nameplates add up to, and most of that in five months.
Two winds in one year
India's wind arrives with the south-west monsoon. In the ministry's count for 2025-26, the four months from June to September made 52% of the year's wind power.[3]
The two seasons differ in size. They also keep different hours.
In the monsoon wind peaks in the late afternoon. In winter it peaks near midnight, at under half the height
Wind generation at each quarter-hour of the average day, in gigawatts (GW)
From June to September 2026 the fleet made 472 GWh a day. Its low point came at 7:30 am, at 15.4 GW, and its high at 5:30 pm, at 23.3 GW. At 10 pm it was still giving 20.9 GW. That is the useful shape. The wind builds through the afternoon as solar fades, and it holds through the evening.
From December to February the fleet made 160 GWh a day, a third as much. The shape turns over. Wind is lowest in the afternoon, 3.8 GW at 2:45 pm, and highest at 11 pm, at 9.5 GW.
In winter 59% of wind's power comes after dark. In the monsoon 46% does. So the season in which wind is most a night source is the season in which there is least of it.
The monsoon is also when cloud dims the solar plants. In July 2026 wind made 584 GWh a day on the grid operator's meters and solar made 517. In August it was 548 against 537. Those were the only two months of the twelve in which wind made more than solar. The year before, by the ministry's count, there were 3: June, July and August 2025.
The evening peak
A grid is built for its hardest hour, and in India that hour now comes after sunset. So we took every evening of the year, found the quarter-hour after 6 pm when the country was using the most power, and read what wind was giving at that moment.
On 57 evenings the whole fleet gave under 5 GW at the peak
Wind generation at the quarter-hour of highest demand after 6 pm, every evening from 1 November 2025 to 31 October 2026, in gigawatts (GW)
On the middle evening of the year wind gave 9.6 GW. On 94 evenings it gave more than 20, every one of them between May and September. On 57 it gave under 5, and 55 of those fell between November and March.
The stillest was 30 December 2025. At that evening's peak India was using 213.9 GW and the wind fleet was giving 1.6, which is 0.7% of it. The windiest was 12 July 2026, at 33.3 GW, or 13.7% of what the country was using. Earlier that afternoon the fleet touched 36.6 GW, the highest reading of the year.
| Month | Demand on the middle evening, GW | Wind on the middle evening, GW | Wind's share on the middle evening | Evenings under 5 GW |
|---|---|---|---|---|
| November 2025 | 196 | 5.0 | 2.5% | 13 |
| December 2025 | 208 | 4.3 | 2.0% | 20 |
| January 2026 | 211 | 5.8 | 3.0% | 10 |
| February 2026 | 212 | 5.9 | 2.8% | 6 |
| March 2026 | 214 | 7.1 | 3.3% | 6 |
| April 2026 | 227 | 10.3 | 4.5% | 0 |
| May 2026 | 234 | 15.3 | 6.8% | 0 |
| June 2026 | 246 | 20.2 | 8.4% | 0 |
| July 2026 | 239 | 25.3 | 10.8% | 0 |
| August 2026 | 240 | 25.6 | 10.7% | 0 |
| September 2026 | 234 | 15.0 | 6.3% | 0 |
| October 2026 | 229 | 6.2 | 2.8% | 2 |
The middle evening is the one with as many evenings above it as below, taken separately for each column. Source: Grid Controller of India, daily reports, read through an open copy. The sorting is ours.
There is some luck in the table. India's evenings are heaviest in the wind's own season. The middle evening peak was 246 GW in June and 208 GW in December. Wind is weakest when the evening is lightest.
October is where the luck runs out. The monsoon has gone, the evening peak is still 229 GW, and wind on the middle evening is back to 6.2 GW.
Wind is also growing more slowly than the evening. At 10 pm, on the average day of April to September, India used 21.2 GW more in 2026 than in 2025. Wind supplied 2.9 GW of the increase. Coal supplied 16.4.
Where the turbines stand
Seven states hold 59.3 of India's 59.5 GW of wind. Gujarat has 17.3 GW, which is 29% of the fleet, and Tamil Nadu 12.3. All seven lie in the west and south of the country, under the same monsoon.
That is why the fleet rises and falls as one. On the evening of 30 December 2025 it gave 2.7% of its rating. No windy state was covering for a still one.
| State | Wind capacity, GW | Generated in 2025-26, billion units | Could be built, GW | Turbines under 2 MW, GW |
|---|---|---|---|---|
| Gujarat | 17.3 | 33.7 | 181 | 4.7 |
| Tamil Nadu | 12.3 | 24.2 | 95 | 7.4 |
| Karnataka | 9.0 | 18.8 | 169 | 3.0 |
| Maharashtra | 6.5 | 8.6 | 174 | 3.4 |
| Rajasthan | 5.8 | 7.3 | 284 | 2.9 |
| Andhra Pradesh | 4.6 | 8.9 | 123 | 2.4 |
| Madhya Pradesh | 3.8 | 4.7 | 55 | 1.6 |
| India | 59.5 | 106.7 | 1,164 | 25.4 |
Capacity is as on 31 October 2026. “Could be built” is the National Institute of Wind Energy's estimate at a hub height of 150 metres. Turbines under 2 MW are those the ministry listed in 2023 as fit to replace. Sources: Ministry of New and Renewable Energy; National Institute of Wind Energy.
Room is not what holds wind back. The National Institute of Wind Energy puts what India could build at 1,164 GW, with turbines 150 metres tall.[4] The fleet is 5% of that. Rajasthan has the most room, 284 GW, and 5.8 GW of turbines.
Why the fleet grows slowly
In 2025-26 India added 6.05 GW of wind, the most it has added in one year.[5] The best year before that was 2016-17, with 5.5 GW. In between, the yearly figure fell as low as 1.1 GW, in 2021-22.[6] From April to October 2026 India added 3.4 GW.
Wind's record year is half the rate the 2030 mix needs
Gigawatts (GW) of wind capacity added in each financial year, and the yearly rate needed from November 2026 to March 2030
The Central Electricity Authority's mix for March 2030 has 99.9 GW of wind in it.[7] The Authority says its capacities are not the country's targets. They are the study behind the 500 GW goal. Against a fleet of 59.5 GW, the mix leaves 40.4 GW to build in 41 months, or 11.8 GW a year.
On 30 June 2026, 27.7 GW of wind was under construction, counting the wind in hybrid plants.[8] If every megawatt of it is finished, the fleet reaches about 87 GW.
Three things slow it.
- Buyers want the evening, and batteries now sell it. The ministry said in November 2025 that solar plants with storage were proving more economical than wind-and-solar hybrids, because they can supply the hours of peak demand.[9] A battery delivers the same evening in December as in July. A turbine cannot choose.
- The sea has no turbines. A subsidy of Rs 7,453 crore is on offer for 1 GW of offshore wind. The first tender, for 500 MW off Gujarat, was issued in September 2024 and closed on 31 July 2025 without a single bid. On 29 July 2026 the ministry told Parliament that no offshore project had been awarded.[10]
- The best sites hold the smallest machines. Most turbines put up before 2000 are smaller than 1 MW and stand on sites with strong wind, the ministry's own policy says.[11] Their hubs are 30 to 60 metres high. New ones stand at 120 to 140. The policy counts 25.4 GW of turbines under 2 MW that could be replaced, 9.9 GW of them under 1 MW. Tamil Nadu has 7.4 GW, equal to 60% of its fleet today. We found no official count of how many have been replaced.
What it would take
Take the Authority's mix as the measure.
- Wind in the mix for March 2030
- 99.9 GW
- Standing on 31 October 2026
- 59.5 GW
- Under construction, June 2026
- 27.7 GW
- To build each year until March 2030
- 11.8 GW
- Most built in one year
- 6.05 GW
Suppose all of it were built, and the new turbines behaved as the present ones did this year. On the middle evening of July the fleet would give about 42 GW at the peak. On the middle evening of December it would give about 7.
So more wind answers the monsoon evening, which is the heaviest of the year, and leaves the winter evening almost where it is. That is no argument against building it. It says what to build beside it: wind for the months when demand is highest, and stored water or batteries for the still evenings from November to March.
Three numbers will show which way it goes: the gigawatts of wind added each year, the megawatts of old turbines replaced, and what the fleet gives at the evening peak in December.
What this does not show
- One year. Wind differs from one monsoon to the next. July 2025 made 456 GWh a day against 584 in July 2026, and the fleet grew in between.
- The country, not the states. The readings are totals for India. They cannot say which state was still on a given evening.
- Wind that was told to stop. The readings show what turbines sent out. Power held back for want of a line or a buyer is not in them.
- Our definitions. After dark is 7 pm to 6 am in every month, though sunset moves. The evening peak is the quarter-hour of highest demand after 6 pm. The line at 5 GW is a round number we chose.
- Missing days. The year has 358 days with all 96 readings out of 365. The rest are left out.
- A growing fleet. The fleet was 56.1 GW in March 2026 and 59.5 GW in October. We measured against October, which understates a little what each gigawatt gave. New turbines are also taller than the average of the old fleet, so a larger fleet may do better than our scaling says.
- Solar on the operator's meters. The monthly comparison with solar uses the grid operator's readings, which may leave out panels on roofs.
- Room is an estimate. What could be built is the Institute's reckoning of land and wind, not a list of sites with lines and buyers.
- No person has checked these figures against the sources. Treat them with care.
Sources
- Grid Controller of India, daily power supply position report: readings every 15 minutes of generation by type of plant and of demand met. Read through an open copy of the reports. We have not yet read the operator's terms for reuse.
- Ministry of New and Renewable Energy, State-wise (location based) installed capacity of renewable power as on 31.10.2026: wind capacity in every state.
- Ministry of New and Renewable Energy, Renewable Energy Statistics 2025-26: wind and solar generation in each month of 2025-26 (table 5.4) and wind generation by state (table 9.2).
- National Institute of Wind Energy, India's wind potential atlas at 150 metres, 2023: the wind capacity that could be installed in each state.
- Ministry of New and Renewable Energy, “India ranks third globally in renewable energy installed capacity”, Press Information Bureau, 8 April 2026: wind capacity added in 2025-26.
- Ministry of New and Renewable Energy, Physical Achievements, as on 31 October 2026: wind capacity added in each financial year from 2014-15, and from April to October 2026.
- Central Electricity Authority, Report on Optimal Generation Capacity Mix for 2029-30, Version 2.0, April 2023, table 6: the wind capacity in its mix for March 2030.
- Ministry of Power, reply to Lok Sabha unstarred question 3209, 6 August 2026: wind capacity under construction, with the wind part of hybrid plants, as on 30 June 2026.
- Ministry of New and Renewable Energy, statement on renewable capacity awaiting power sale agreements, Press Information Bureau, 4 November 2025: why buyers are choosing solar with storage.
- Ministry of New and Renewable Energy, reply to Lok Sabha unstarred question 1676, 29 July 2026: the support on offer for offshore wind, and the tender that drew no bid.
- Ministry of New and Renewable Energy, National Repowering and Life Extension Policy for Wind Power Projects, December 2023: the old turbines that could be replaced, by state, and their heights.
Grid Search is the energy project of Seed 42 Labs. Our subject is electricity: what generates it, in India and the rest of the world.