How far is India from 500 GW of non-fossil power?

About 188 GW, with four years left. At last year's pace India gets there. The wider gap is in electricity: non-fossil plants are 55% of the capacity, made 29% of the power last year, and supply about 18% of it at night.

14 November 2026 · Capacity counted on 31 October 2026

Where the count stands

On 31 October 2026 India had 312.24 gigawatts (GW) of power plants that do not run on coal, gas or oil.[1] The target for 2030 is 500. That leaves 187.8 GW to build.

Solar is more than half of what is counted: 174.6 GW. Wind is 59.5, large hydro 52.3, biomass 11.9, small hydro 5.2 and nuclear 8.8.

India's non-fossil capacity tripled in ten years, and solar did most of it

Gigawatts (GW) of non-fossil capacity at 31 March of each year, by source, then on 31 October 2026, beside the target for 2030

0100200300400500gigawatts20162017201820192020202120222023202420252026Oct 202696312500188 to go2030
SolarWindBiomass and small hydroLarge hydroNuclearThe target: a promise, not a count
Large hydro includes pumped storage. Sources: Ministry of New and Renewable Energy, Renewable Energy Statistics 2025-26 and Physical Achievements as on 31 October 2026.

Ten years earlier, on 31 March 2016, the count was 95.7 GW.[2] Of the 217 GW added since, 167 were solar. That is 77% of the climb. Wind added 33 GW, large hydro 9.5 and nuclear 3.0.

Non-fossil plants are now the larger part of the fleet. On 30 September 2026 the Central Electricity Authority put them at 55.1% of 559 GW.[3]

What was promised

The number comes from one sentence, spoken at the climate summit in Glasgow on 1 November 2021: “India will reach its non-fossil energy capacity to 500 GW by 2030.”[4]

It is not in the pledge India filed with the United Nations. That pledge, of August 2022, is a share: “about 50 percent cumulative electric power installed capacity from non-fossil fuel-based energy resources by 2030”.[5] India passed that share in June 2025, five years early.[6] The next pledge, for 2035, is about 60 percent.[5]

So 500 GW is a goal India set for itself, and it has already been raised. On 2 November 2026 the Prime Minister said nearly 300 GW had been reached and announced a goal “to add another 500 Gigawatts of new non-fossil capacity over the next 10 to 11 years”.[7] The ministry's count for two days earlier, published afterwards, is 312.2.

“By 2030” can be read two ways. The Central Electricity Authority plans in financial years, and its year 2029-30 ends on 31 March 2030. That is 41 months from the count. The end of 2030 is 50 months away.

The pace it needs

To add 187.8 GW by March 2030, India must build 55.0 GW a year. By December 2030 it must build 45.1.

Only one year so far has matched the pace the target needs

Gigawatts (GW) of non-fossil capacity added in each financial year, and the yearly rate needed from November 2026 on the two readings of 2030

02040602016-172017-182018-192019-202020-212021-222022-232023-242024-2529.52025-2655.355 a year to March 203045 a year to December 2030
Each bar is the difference between two year-end counts, except 2025-26, which is the ministry's own figure. The dashed lines are our arithmetic, not a forecast. Sources: Ministry of New and Renewable Energy; Press Information Bureau, 8 April 2026.

India has built at that pace once. In 2025-26 it added 55.29 GW, the most in any year and nearly double the 29.5 of the year before.[6] Before that the most was 20.0.

This year is on a similar course. From 1 April to 31 October 2026, seven months, 28.8 GW were added.[1] Last year the first six months brought about 25 GW of renewables, and the second six about as many again.[8][2]

So the count is within reach on either reading, if a pace India has held for one year holds for four more.

What 500 was meant to be made of

In April 2023 the Central Electricity Authority worked out the cheapest mix of plants that would meet India's demand in 2029-30. Its non-fossil plants add up to 500.6 GW.[9] The report carries a caution on its first pages: the capacity it projects “should not be in any way considered as target of the country”. It is still the only official account of what 500 GW would contain.

Solar is ahead of the 2030 mix. Wind and nuclear are not

Gigawatts (GW) of each non-fossil source on 31 October 2026, inside what the Central Electricity Authority's study put in its mix for March 2030. On the right, what is left to build, the yearly pace that needs, and the most ever added in a year

Source, GW now of GW in the mixStill to build

In place on 31 October 2026The Authority's mix for March 2030: a study, not a target
Hydro is large hydro with pumped storage. The pace is the gap spread over the 41 months to March 2030, and is ours. Sources: Ministry of New and Renewable Energy; Central Electricity Authority, Optimal Generation Capacity Mix for 2029-30.

Solar needs 34.5 GW a year and added 44.6 last year. It is the one source running ahead.

Wind needs 11.8 GW a year. The most India has ever added in a year is 6.05, in 2025-26.[6] Nuclear needs 6.7 GW more. The Ministry of Power says 8,000 MW is under construction and “targeted to be completed by 2031-32”.[10] Hydro and pumped storage need 20.5 GW, and the dates of the pumped storage plants have already slipped.

The International Energy Agency expects the shortfall to be made up in solar. Its forecast for 2030 has solar above 350 GW, wind near 90 and hydro at 75, and it expects India to meet the 500 GW target on time.[11] That is at least 57 GW more solar than the Authority's mix, and about 10 GW less wind.

The count would be the same. The hours would not. A wind turbine and a reactor generate after dark, and a solar panel does not. What happens on India's grid after sunset is set by that difference.

What is being built

The Ministry of Power told the Lok Sabha what was under construction on 30 June 2026.[10]

Non-fossil capacity under construction, 30 June 2026
KindMWAs the ministry describes it
Solar119,580includes the solar part of hybrid plants
Wind27,720includes the wind part of hybrid plants
Hydro12,973of 16,448 MW projected for 2026-27 to 2031-32
Pumped storage15,870counted as hydro when built
Nuclear8,000targeted to be completed by 2031-32

The ministry gives 147,720 MW for all renewables under construction, slightly more than solar and wind together. Source: Ministry of Power, reply to Lok Sabha unstarred question 3209.

Renewables, hydro and pumped storage under construction come to 176.6 GW. A month after that list, on 31 July, the installed count was 300.50 GW.[12] Together they make about 477, with the nuclear plants due after 2030 left out. A little of what was under construction in June was finished in July, so the true sum is slightly lower.

What is being built does not reach 500 on its own. The ministry lists a further 47,830 MW of renewables “at various stages of planning and targeted to be completed by 2029-30”, 44,440 MW of it solar. The target needs all of the first list and half of the second.

The same reply lists 47,545 MW of coal plants under construction and 16,000 MW more awarded. The Authority's mix for March 2030 has 251.7 GW of coal and lignite, against 231.4 today.[9][3] The target was never a plan to close coal plants. It is a plan to build more of everything else.

Buyers and wires

Two things stand between a plant on a list and a plant on the grid. It needs a buyer, and it needs a line.

On 30 September 2025 the central agencies that run renewable auctions had awarded 43,942 MW for which no distribution company had signed to buy the power.[8] The ministry gave the reason itself. Buyers now prefer solar with storage, and there is “a reduced demand for plain solar power”. It ruled out cancelling the awards in bulk, and changed the bidding rules so that an award unsigned after 12 months can be cancelled.

Lines are the other limit. In July 2026 the ministry told the Lok Sabha that about 21 GW of wind and solar was sending power out on temporary access to the grid, and that “the evacuation of roughly 12 GW is restricted for limited durations during peak solar generation”.[13] The cause it gave is a mismatch between the dates plants were finished and the dates their lines were.

Over 2025-26 about 6,900 gigawatt-hours were held back this way. Wind and solar generated 281 billion units that year, so about one unit in 41 was lost.[2]

A plant counts toward 500 GW from the day it is commissioned, whether or not its line is ready.

Capacity is not electricity

The target counts what plants could generate at full power. It does not count what they generate. On 31 March 2016 non-fossil plants were 31.2% of India's capacity, and in the year to that date they made 19.2% of its electricity. Ten years later they were 53.2% of the capacity and made 29.0%.[2] The capacity share rose 22 points. The electricity share rose 10.

What each kind of plant generated in 2025-26
KindCapacity, 31 March 2026, GWGenerated, billion unitsShare of the year at full power
Coal, gas and diesel249.31,307.160%
Nuclear8.855.274%
Large hydro51.4167.239%
Solar, wind, biomass and small hydro223.3310.618%

The last column is generation divided by what the average of the capacity at the start and end of the year would generate running all year, and is ours. A billion units is a terawatt-hour. Source: Ministry of New and Renewable Energy, Renewable Energy Statistics 2025-26.

A gigawatt of coal, gas and diesel plant generated more than three times what a gigawatt of solar, wind, biomass and small hydro did. The sun is up for half the day and high for less, and wind comes in seasons.

The share also moves through the day. The grid operator's readings, taken every 15 minutes, show what was generating at each moment.[14]

Non-fossil plants are 55% of India's capacity. Before dawn they supply 17% of its power

Share of India's generation from solar, wind, hydro and nuclear plants at each quarter-hour of the average day, 1 November 2025 to 31 October 2026, with their share of installed capacity

0%20%40%60%Midnight6 amNoon6 pmMidnightShare of capacity: 55.1%44.0% at 1 pm17.0% at 4:30 amShare of generation
Averaged over 358 complete days of readings. Biomass is not separated in the readings and is left out, so the line runs a little below the official yearly share. Sources: Grid Controller of India, through an open copy; Central Electricity Authority, capacity as on 30 September 2026.

At 1 pm on the average day these plants supplied 44.0% of India's power. At 4:30 am they supplied 17.0%. Across the hours with no sun the average was 18.4%. At no time of day did the share of electricity come near the share of capacity.

Reaching 500 GW will not close that gap, and the Authority's study says so. In its mix for 2029-30 non-fossil plants are 64% of capacity and “around 44%” of generation.[9] The International Energy Agency, which leaves nuclear out, expects renewables to supply 35% of India's electricity in 2030.[11]

The same study pairs the 500 GW with storage: 41.7 GW of batteries and 19.0 GW of pumped storage, holding 336 gigawatt-hours.[9] Storage is not counted in the target. It is what would move the noon share into the night.

What it would take

Left to build, from 31 October 2026
187.8 GW
Needed each year to March 2030
55.0 GW
Needed each year to December 2030
45.1 GW
Added in 2025-26, the record
55.3 GW
Wind needed each year, against its best year
11.8 against 6.1 GW
Non-fossil share of capacity, and of generation in 2025-26
55% and 29%

India is about 188 GW from 500, and on last year's pace it arrives in 2030.

What arrives will not be what was drawn. It will hold more solar and less wind and nuclear than the mix the planners studied, some of it will wait for lines, and it will supply well under half of India's electricity. Through the night, coal will still do most of the work.

So the count is worth reading beside three others: the gigawatts of wind and nuclear added each year, the gigawatt-hours held back for want of a line, and the non-fossil share of generation after dark.

What this does not show

  • The pace is arithmetic. We divided what is left by the months remaining. It is not a forecast, and capacity does not arrive evenly through a year.
  • The mix is a study. The Central Electricity Authority's mix for 2029-30 dates from April 2023 and is not a target. No official document splits the 500 GW by source.
  • Dates do not line up. The list of plants under construction is for 30 June 2026, the count beside it for 31 July, and the latest count for 31 October. Fossil capacity is for 30 September.
  • Counts differ between offices. The Authority has taken some plants long out of service off its list, 100 MW of nuclear among them, so year-end differences and the ministry's own figures for additions do not match exactly.
  • The unsigned awards are a year old. The 43,942 MW is the count of 30 September 2025. We found later figures only in trade reports, and did not use them.
  • The day is an average. The share by time of day is a mean over 358 days and hides the seasons. It counts solar, wind, hydro and nuclear, and leaves out biomass.
  • Forecasts are not counts. The International Energy Agency's figures for 2030 are its own model's. We read its summary, not the full report.
  • No person has checked these figures against the sources. We have not yet read the grid operator's terms for reuse. Treat the figures with care.

Sources

  1. Ministry of New and Renewable Energy, Physical Achievements, as on 31 October 2026: installed capacity of each renewable source, large hydro and nuclear, and what was added since 1 April. The page labels that last column 2025-26; the figures are for April to October 2026.
  2. Ministry of New and Renewable Energy, Renewable Energy Statistics 2025-26: installed capacity at each 31 March from 2016 (tables 1.1 and 2.1) and generation in each year from 2015-16 (tables 3.1 and 4.1).
  3. Central Electricity Authority, Installed capacity of the country as on 30.09.2026: every kind of plant, fossil and non-fossil, on one page.
  4. Prime Minister's Office, National Statement at the COP26 summit in Glasgow, 1 November 2021.
  5. Government of India, India's Updated First Nationally Determined Contribution, August 2022, and the contribution for 2031 to 2035, both as filed with the United Nations climate convention.
  6. Ministry of New and Renewable Energy, “India ranks third globally in renewable energy installed capacity”, Press Information Bureau, 8 April 2026: capacity on 31 March 2026, what was added in 2025-26, and the non-fossil share of generation.
  7. Prime Minister's Office, “Prime Minister inaugurates Bharat Renewable Energy Summit & Expo 2026”, Press Information Bureau, 2 November 2026.
  8. Ministry of New and Renewable Energy, “No blanket cancellations of REIA-awarded projects”, Press Information Bureau, 4 November 2025: capacity awarded without a buyer, and what was added in the first half of 2025-26.
  9. Central Electricity Authority, Report on Optimal Generation Capacity Mix for 2029-30, Version 2.0, April 2023: the capacity of each source in its mix (tables 6 and 10), storage, and the share of generation.
  10. Ministry of Power, reply to Lok Sabha unstarred question 3209, 6 August 2026: capacity under construction and planned, by kind, as on 30 June 2026.
  11. International Energy Agency, India Renewable Energy Market Report 2026, executive summary: its forecast of renewable capacity and generation in 2030.
  12. Ministry of New and Renewable Energy, release on crossing 300 GW of non-fossil capacity, Press Information Bureau, 9 August 2026: the count on 31 July 2026.
  13. Ministry of New and Renewable Energy, reply to Lok Sabha unstarred question 1782, 29 July 2026, on renewable energy and transmission.
  14. Grid Controller of India, daily power supply position report: readings every 15 minutes of generation by type of plant. Read through an open copy of the reports. We have not yet read the operator's terms for reuse.

Grid Search is the energy project of Seed 42 Labs. Our subject is electricity: what generates it, in India and the rest of the world.