Can pumped storage carry India's evening?
Not yet, and not alone. Since April the plants that can pump have generated about 25 GWh a day. Holding coal level through an average summer day takes about 170. The 12 plants under construction would bring pumped storage to 137, on dates that have already slipped.
What ten plants did since April
India counts ten pumped storage plants, 7,426 megawatts (MW) between them.[1] Each is two reservoirs at different heights with a power station in between. When electricity is plentiful the station pumps water uphill. When it is scarce the water runs back down through the turbines.
Two of the ten cannot do the first half. The Central Electricity Authority's list carries a footnote: Sardar Sarovar and Kadana, both in Gujarat and 1,440 MW between them, “are not operational in pumping mode”.[1] They generate as any dam does. The Authority expects Sardar Sarovar to pump by June 2028.[2] That leaves 5,986 MW that can store anything.
What those plants did with it can be read from the Authority's daily generation report, which prints what every station has generated since 1 April.[3] To 11 November 2026 that is 225 days.
India's pumped storage plants: what is built, what it generated, and what is coming
Bars are megawatts (MW). For plants in operation, gigawatt-hours (GWh) generated per day from 1 April to 11 November 2026. For plants under construction, the month each is expected
Operating, and can pumpGWh a day
Operating, cannot pumpGWh a day
Under constructionExpected
One plant did most of the work. Pinnapuram in Andhra Pradesh, commissioned between June and October 2025, generated 10.3 GWh a day. That is 6.2 hours at full power, every day, for seven months. It is 28% of the megawatts that can pump and 41% of what they generated.
The older plants ran less. Purulia in West Bengal, commissioned in 2007, averaged 3.5 hours a day at full power, and Tehri in Uttarakhand 4.1. Kadamparai in Tamil Nadu averaged 0.4: on the day of the report 300 of its 400 MW were out of service, and the regional power committee's minutes expect two of its four units back by January 2027.[3][4]
Together the 8 plants that can pump generated 25.1 GWh a day. That is the most they can have stored, because six of them sit on rivers and some of their water arrived without being pumped. The two that stand off any river generated 13.5 GWh a day, and all of that was pumped uphill first.
For scale: India's coal plants generate about 3,659 GWh on an average summer day, and every grid battery in operation at the end of September held 14.5 GWh.[5] Pumped storage is the larger store today, and still under 1% of coal's day.
What pumped storage is
It is the oldest way to store electricity at scale, and the idea is not new to India. The reversible machines at Nagarjuna Sagar were commissioned between 1980 and 1985.[1] Four things set it apart from a battery.
- It runs for longer. The Authority designs for six to eight hours at full power.[2] The projects under construction in June came to 15,870 MW and 95,220 megawatt-hours: six hours each.[6] India's operating batteries average under three.
- It loses more. The tariff rules entitle a buyer to 75% of the energy used in pumping.[7] Real plants do a little better. Purulia has averaged 77.69% since 2007.[8] Tehri, with newer variable-speed machines, pumped 1,038 GWh from April to October 2026 and generated 871, of which 37 was river water: 80.4%.[9] A battery contract asks for 85%.
- It lasts. The Authority puts a plant's life at about 100 years.[2] The contracts described below run for 40.
- It needs a hill and water. A plant on a river shares its water with irrigation and the monsoon. A plant off any river, with two reservoirs of its own, keeps the same water going round. The Authority calls the second kind off-stream closed loop.
India's ordinary dams already do half of this job. They cannot pump, but they can wait. From April to September 2026 hydro generation on the average day was lowest at 1:15 pm and highest at 7:45 pm.[10]
Hydro holds its water for the evening
Hydro generation by time of day, gigawatts (GW), averaged over 182 days from April to September 2026
That is 12.6 GW more hydro in the evening than at midday, a larger shift than any storage makes on India's grid. What a dam cannot do is fill itself again at noon. Pumped storage is a dam that can.
The world had 201 GW of pumped storage at the end of 2025, and 243 GW more under construction, 218 GW of that in China.[11] India has 16.8 GW under construction.[1]
It used to fill at night
For most of their lives India's pumped plants filled after midnight, when demand was low and coal plants had power to spare. On a typical day in 2016 Purulia pumped from about 1 am to 10:30 am and generated between 6 pm and midnight. Ghatghar and Kadamparai pumped from 1 am to 5:30 am.[12]
Solar has moved the hour. At 2:09 pm on 13 May 2026 the frequency of the southern grid dipped when solar output dropped. The committee that reviews such events recorded what was drawing power at that minute: “around 1800 MW of pumping load”, about 1,600 MW of it at Pinnapuram and about 210 MW at Nagarjuna Sagar.[4] Purulia's owner now says its daytime pumping “may be harnessed from infirm Solar Power”.[8]
The price explains it. On the day-ahead market from April 2025 to July 2026, power in solar hours averaged about Rs 2.2 a unit and in the evening peak about Rs 6.57.[13] A plant that returns 75% needs Rs 2.93 of noon power for each unit it sells after dark. That leaves about Rs 3.64 a unit to pay for the plant.
The hour it fills decides what it does to coal. Filled from solar that would otherwise have no buyer, every unit it returns in the evening is a unit coal does not generate. Filled at night by coal plants, it makes those plants steadier and burns a little more coal, because a quarter of what goes in is lost. Our piece on batteries found the same rule.
Twelve more, and their dates
The Authority lists 12 plants under construction, 16,820 MW.[1] That is more than twice everything operating. 9 of the 12 are off any river, and four of them, 7,000 MW, are in the hills of Maharashtra's Western Ghats: Bhavali, Bhivpuri, Tarali and Karjat. In August the Ministry of Power counted 11 plants and 15,870 MW; the twelfth, Kamalapadu, is on the Authority's list only.[14]
Their dates move. Set the ministry's list of December 2025 beside the Authority's list now. Nine plants are on both, and 4 have slipped in under a year.[15][1]
| Plant | MW | Expected, December 2025 | Expected now | Months later |
|---|---|---|---|---|
| KundahTamil Nadu | 500 | April 2026 | February 2027 | 10 |
| ChitravathiAndhra Pradesh | 500 | October 2026 | February 2027 | 4 |
| BhivpuriMaharashtra | 1,000 | October 2028 | February 2029 | 4 |
| SharavathyKarnataka | 2,000 | December 2029 | May 2032 | 29 |
Sources: Ministry of Power, reply of 18 December 2025; Central Electricity Authority, status note of October 2026. The months are ours.
The daily report shows the same thing from another side. The generation programme set for this year expected Gandhi Sagar in Madhya Pradesh to have generated 580 GWh by 11 November 2026 and Kundah in Tamil Nadu 254. Neither has generated anything.[3] Gandhi Sagar, at 1,920 MW, is now expected in December 2026.
Two plants that did finish show how wide the range is.
- Tehri took four decades. The Authority cleared its design in May 1985. The government approved it in July 2006 at Rs 1,658 crore. Its first unit entered service in June 2025 and its fourth in April 2026. By March 2026 Rs 8,230 crore had been spent, about Rs 8.2 crore a megawatt.[1][9][16]
- Pinnapuram took three and a half. The Authority cleared it in April 2022 and all eight units were running by October 2025.[1] It is off any river, with two reservoirs built for it. The Authority puts the build time of such a plant at 3.5 to 4 years.[2]
Sharavathy in Karnataka, 2,000 MW, is the hard case. It would sit inside a wildlife sanctuary that shelters the lion-tailed macaque. The Karnataka High Court stayed it in March 2026, and in July the central government told the court that a committee of the national wildlife board had recommended against it.[17] The Authority still lists it as under construction, for May 2032.[1]
Asked what holds these projects back, the ministry listed “difficulties in carrying out survey and investigation activities in forest areas, issues related to land acquisition, Rehabilitation and Resettlement (R&R), Eco-Sensitive Zones, high initial capital costs, and delays in the creation of essential infrastructure”.[18]
Against that record stands a roadmap. The Authority plans 105.6 GW of pumped storage by March 2036.[2] India has built 7.4 GW in all, and none of it between 2008 and 2025.
What India has built, and what the roadmap asks for
Pumped storage in operation, gigawatts (GW). The dashed and dotted lines are plans, not forecasts
The two lines part within three years. If every plant under construction arrives on its date, India has 22.2 GW in March 2030. The roadmap has 31.8. A year later the roadmap has 53.0, and nothing more under construction is due.
Add the 8 projects the Authority has cleared and nobody has started, 10.4 GW, and the total is 32.6 GW.[1] The other 20 GW the roadmap wants by March 2031 would have to come from projects still being surveyed, in four years and four months. The quickest kind of plant takes three and a half to four after its clearances.
The national plan of 2023 asks for less: 26.69 GW and 175 GWh by March 2032.[19] What is under construction reaches 22.2 GW by then if no date moves again.
There is no shortage of sites. The Authority has identified 322 of them, 347 GW, and 201 GW of that is off any river.[1]
What it would do to coal's evening
To see what this much storage is good for, we ran it on paper, the way the battery piece did. Take coal's average day from April to September 2026.[10] Give the storage one job: keep coal generation as level as it can. Once a day it gives back into the hours when coal is highest and fills in the hours when coal is lowest.
Every pumped plant is counted at 6 hours of its full power and returns 75% of what it takes, the floor in the tariff rules. Batteries return 85%. This is a model, not a forecast, and the ways it differs from a real grid are listed at the end.
Coal's average day, with the storage India has started to build
Coal and lignite generation in gigawatts (GW), April to September 2026. The scale starts at 100. Modelled
| Storage | Holds, GWh | Can deliver, GW | Coal's highest | Coal's lowest |
|---|---|---|---|---|
| No storage | 171.8 | 120.5 | ||
| Pumped storage that can pump today | 35.9 | 6.0 | 165.8 | 126.5 |
| And pumped storage under construction | 136.8 | 22.8 | 156.7 | 143.3 |
| And batteries operating or under construction | 230.3 | 55.9 | 154.4 | 154.4 |
Gigawatts of coal and lignite generation unless marked. Each row adds to the store in the row above. Modelled, except the first row.
The plants that can pump today take 6 GW off coal's evening high, from 172 GW to 166. With the 12 under construction it comes down to 157, and coal's midday low rises from 121 GW to 143. The gap between coal's midday low and its evening high shrinks from 51 GW to 13.
Add the batteries operating and under construction, and coal stops moving. It runs at 154 GW from midnight to midnight, on 170 GWh delivered each evening, with 61 GWh of storage left over.
That is the finding. India does not need to win another tender to level coal's summer day. What is operating and under construction is enough on paper, and pumped storage is the larger part of it: 137 GWh of 230.
Two cautions belong beside it. The first row of the model gives today's plants 35.9 GWh a day; since April they have managed at most 25.1. And water loses more than lithium. To give back 137 GWh, the pumps take 182. Filled from new solar, that is 31% more solar than the grid operator metered on the average day. Filled by coal, it is 46 GWh of extra coal generation a day.
The price
A pumped plant costs about Rs 6 crore a megawatt to build, by the Authority's average, and the roadmap comes to Rs 5.8 lakh crore. The Authority writes that the cost is “potentially making it less competitive in terms of cost as compared to BESS”, its term for batteries.[2]
Utilities buy pumped storage the way they buy batteries. A builder bids a yearly fee for each megawatt. The buyer supplies the power for pumping and bears the loss.
In September 2024 Maharashtra's regulator approved 3,000 MW for 8 hours a day over 40 years at Rs 84.66 lakh a megawatt a year, with a loss of 24% in each cycle.[20] In July 2026 the Solar Energy Corporation of India awarded 1,344 MW of 8-hour storage at a fixed charge of Rs 108.4 to 109.8 lakh.[21] That is 29% more in under two years.
Set a battery beside it. In August 2026 West Bengal paid Rs 4.35 lakh a megawatt a month for 4-hour batteries, Rs 52.2 lakh a year.[22]
| Auction | Hours | Rs lakh a MW a year | Rs lakh a MWh a year |
|---|---|---|---|
| Pumped storage, MaharashtraSeptember 2024 | 8 | 84.7 | 10.6 |
| Pumped storage, national tenderJuly 2026 | 8 | 109.1 | 13.6 |
| Batteries, West BengalAugust 2026 | 4 | 52.2 | 13.0 |
The national tender is the middle of its three winning bids. Sources: Maharashtra Electricity Regulatory Commission; Solar Energy Corporation of India; JMK Research. The last column is ours.
Hour for hour, water and lithium now rent for about the same. They are not the same purchase. The pumped contract runs 40 years and delivers eight hours a day. The battery gives back more of what it takes, and can be standing in under two years where a pumped plant needs four at best.
The government has leaned on the scale for water. Pumped plants awarded by June 2028 pay no charge for the national transmission grid for 25 years, the Authority's review of a design has been cut from 90 days to 50, and off-river plants with their own reservoirs no longer need its clearance.[14] On 4 November 2026 the Cabinet approved Rs 14,500 crore towards 92 GWh of storage by 2030-31, 60 GWh of it pumped.[23]
What it would take
- Delivered each evening to hold coal level on the average day, April to September 2026
- 170 GWh
- Generated per day since April by the plants that can pump
- 25.1 GWh
- Of that, by the two plants off any river
- 13.5 GWh
- Pumped storage operating and under construction, at six hours
- 136.8 GWh
- Batteries operating and under construction
- 93.5 GWh
- Pumped uphill each day to give back 137 GWh
- 182 GWh
Pumped storage cannot carry India's evening today. The plants that can pump return about a seventh of what it would take to hold coal level, and one plant finished in 2025 does two-fifths of that.
It can carry most of it by the early 2030s, with batteries doing the rest, if 12 plants arrive on dates that 4 of them have already missed once. The plants worth watching are the ones off any river. Pinnapuram was built in three and a half years and runs a full cycle every day. Tehri took twenty years from its approval, and Sharavathy is in court.
So the fleet is worth counting three ways: the megawatts that can pump, the hours they run each day, and the date on each plant not yet built.
What this does not show
- Generation is not storage. The daily report prints what a plant generated, not what it pumped. On a river, some of the water was never pumped. Only Tehri and Purulia publish their pumping, and no one publishes a total for India.
- Six hours is assumed. No official figure gives the energy the operating fleet can hold. We counted every plant at six hours of full power, the ministry's figure for those under construction.
- One job, one point. The model runs all storage to level coal and treats India as one place. A plant in the Western Ghats cannot relieve a coal plant in Bihar if the line between them is full.
- Only coal moves. Hydro and gas also follow the evening. Storage would take some of their work, and less of coal's than drawn.
- Summer only. The average day covers April to September 2026, and an average day is not any real day. Reservoirs on rivers are fullest after the monsoon and lowest before it.
- Dates as printed. The dotted line assumes every plant under construction arrives on the Authority's date, Sharavathy included.
- Prices are not like for like. The contracts differ in length, in who bears losses and in subsidy. We read the Maharashtra order and the December 2025 reply on copies, not on the regulator's and the Lok Sabha's own sites.
- No person has checked these figures against the sources. We have not yet read the grid operator's terms for reuse. Treat the figures with care.
Sources
- Central Electricity Authority, Status of pumped storage development in India, the edition listed for October 2026, and its list of pumped storage plants in operation: every plant and project above 25 MW, with its size, kind, developer and dates.
- Central Electricity Authority, Roadmap to 100 GW of Hydro Pumped Storage Projects by 2035-36, with figures as on 31 December 2025: the capacity it expects at the end of each year, build times, costs and the obstacles it lists.
- Central Electricity Authority, daily generation report of 11 November 2026, sub-report 2, on the National Power Portal: what each station generated that day and since 1 April, the programme set for it, and the capacity out of service.
- Southern Regional Power Committee, minutes of the 239th meeting of the Operation Coordination Committee, 2026: the pumping load at 2:09 pm on 13 May 2026, and the units out of service at Kadamparai.
- Central Electricity Authority, Status of development and deployment of Battery Energy Storage Systems in India as on 30.09.2026.
- Ministry of Power, reply to Lok Sabha unstarred question 3209, 6 August 2026: “15,870 MW/95,220 MWh Pumped Storage Projects (PSPs) are under construction” as on 30 June 2026.
- Central Electricity Regulatory Commission, Terms and Conditions of Tariff Regulations, 2019, regulation 50(4)(B), read on Indian Kanoon: buyers “shall be entitled to equivalent energy of 75% of the energy utilized in pumping”.
- West Bengal State Electricity Distribution Company, Purulia Pumped Storage Project, read 14 November 2026: generation since 2007, efficiency, dates and cost.
- THDC India, Tehri Pumped Storage Plant (1000 MW), read 14 November 2026: the dates each unit entered service, and pumping and generation from April to October 2026.
- Grid Controller of India, daily power supply position report: readings every 15 minutes of demand met and of generation by type of plant. Retrieved 12 November 2026 through an open copy of the reports. We have not yet read the operator's terms for reuse.
- International Hydropower Association, “The year of the ‘water battery’: global pumped storage capacity surpasses 200 GW”, on its 2026 World Hydropower Outlook, 24 June 2026.
- Center for Study of Science, Technology and Policy, report on pumped hydro energy storage, 2021, citing the Central Electricity Authority: the hours Purulia, Ghatghar and Kadamparai pumped and generated on typical days in 2016 and 2017.
- Central Electricity Regulatory Commission, order in petition 13/SM/2026: the grid operator's analysis of day-ahead prices from April 2025 to July 2026, “solar hours, averaging around ₹2.2 per unit, and evening peak hours, averaging approximately ₹6.57 per unit”.
- Ministry of Power, reply to Lok Sabha unstarred question 3204, 6 August 2026: the projects under construction with their target dates, and the steps taken to support them.
- Ministry of Power, reply to Lok Sabha unstarred question 3092, 18 December 2025, annexure III: the pumped storage projects then under construction and their expected dates. Read on a copy, not on the Lok Sabha's own site.
- THDC India, status of the Tehri pumped storage plant, March 2026: the approval of July 2006 at Rs 1,657.60 crore and the Rs 8,230.08 crore spent to March 2026.
- LiveLaw, “Wildlife Board Expert Panel Recommends Against Proposed Sharavathi Hydropower Project Inside Sanctuary: Centre Informs Karnataka High Court”, 10 July 2026.
- Ministry of Power, reply to Lok Sabha unstarred question 707, 23 July 2026, on what holds pumped storage projects back.
- Ministry of Power, “Grid stability and energy storage”, reply in the Rajya Sabha, 27 July 2026, Press Information Bureau: the National Electricity Plan's storage requirements for 2026-27 and 2031-32.
- Maharashtra Electricity Regulatory Commission, order in case 156 of 2024, 26 September 2024, read on a copy: the state distributor's purchase of 3,000 MW of pumped storage for eight hours a day over 40 years.
- Solar Energy Corporation of India, result of the tender for 1,500 MW and 12,000 MWh of pumped storage (PSP-I): the reverse auction of 9 July 2026.
- JMK Research, EnergyWatts: monthly update on India's energy storage market, September 2026, as hosted by the Institute for Energy Economics and Financial Analysis: battery auction prices to August 2026.
- Prime Minister's Office, “Cabinet approves Rs.14,500 crore Viability Gap Funding Scheme for development of 92 GWh Grid-Scale Energy Storage Systems”, 4 November 2026.
Grid Search is the energy project of Seed 42 Labs. Our subject is electricity: what generates it, in India and the rest of the world.