India wants 100 GW of nuclear power by 2047. Can it build that fast?

It would have to connect 91.2 GW in 21 years. One country has ever done that, and each of India's last three reactors took more than ten years to build. We read the law that opened the sector in December 2025, the plan given to Parliament and the build dates of every reactor India has started, to find what would have to change.

13 November 2026 · Reactor dates from the International Atomic Energy Agency, read that day

In 2000 India had more nuclear power than China

In 2000 India had 2.9 gigawatts (GW) of nuclear power stations and China had 2.3.[1] India had been at it far longer. Its first two reactors, at Tarapur, were connected to the grid in 1969.[2]

By the end of 2025 China had 62.5 GW and India had 8.8. China's reactors made 485 terawatt-hours that year. India's made 54, which was 2.6% of India's electricity.[1]

Nuclear capacity in India and China

Gigawatts (GW) at the end of each year, 2000 to 2025

02040602000201020202025India 2.9, China 2.3China 62.5India 8.8
Ember, Yearly electricity data.

The government now wants 100 GW by 2047.[3] In August 2026 it told the Lok Sabha that 24 reactors with 8,780 megawatts (MW) were in operation.[4] That leaves 91.2 GW to connect in the 21 years from 2027 to 2047, which is 4.3 GW a year.

India's best year was 2013, when one 1,000 MW reactor at Kudankulam was connected. Its best ten years, 2016 to 2025, added 3.1 GW in all.[2] The target asks for more in every single year than India has added in any ten.

Has anyone built that fast? The International Atomic Energy Agency (IAEA) records the day each power reactor in the world was first connected. For India and for five countries with large fleets, we added up the most capacity each has connected in any 21 years in a row.

The most nuclear capacity connected in any 21 years
CountryYearsConnected, GW
United States1970 to 1990113.1
France1977 to 199765.6
China2006 to 202657.2
Japan1976 to 199638.9
South Korea1985 to 200516.4
India2005 to 20256.1
What India's target needs2027 to 204791.2

Gross capacity of reactors first connected in those years, including reactors since closed. China's years run to 13 November 2026. Worked out by us from the IAEA's Power Reactor Information System.

The United States did it once, between 1970 and 1990. France, in the 21 years in which it built most of its fleet, connected 65.6 GW. China's last 21 years come to 57.2 GW, and it has 36 more reactors under construction, with 42.1 GW.[2]

This is also not India's first target. An earlier plan aimed at 10,000 MW by 2000.[5] India had 2.7 GW that year. In 2011 the targets were 20,000 MW by 2020 and 63,000 MW by 2032.[6] In 2020 India had 6.7 GW. Asked about the 63,000 MW in February 2023, the government answered with a figure of 22,480 MW by 2031.[7] Today that figure is 22,380 MW by 2031-32.[4]

What India built, and what it aimed at

Nuclear capacity in gigawatts (GW), 1969 to 2026, and each target set for it

0255075100gigawatts197019902010203020474.3 GW a year0.3 GW a year10 GW by 200020 GW by 202063 GW by 203222.4 GW by 2031-32100 GW by 2047Built: 8.78
BuiltA targetA pace carried forward, not a forecast
The solid line is the capacity of India's reactors, each counted from the year it was first connected and at today's rating. A ring is a target; the grey rings were missed or replaced. The two dashed lines carry a pace forward from 13 November 2026 and are not forecasts. The upper one is what the target needs. The lower one is India's pace from 2016 to 2025, which reaches 15 GW in 2047. Capacity from the IAEA; targets from the sources in the text.

The plan given to Parliament has three parts. Projects already in hand take capacity to about 22 GW by 2031-32. The state's Nuclear Power Corporation of India adds another 32 GW after that, to reach about 54 GW by 2047. The remaining 46 GW is to come from other public companies, state governments, private companies and joint ventures.[3] A reply six days later put that last part at 45 GW.[8] Until December 2025 the law did not allow a private company to own a reactor at all.[9]

How long India takes to build one

A reactor counts toward the target on the day it is first connected to the grid. So the pace comes down to two numbers: how many reactors are under construction at once, and how long each one takes.

The IAEA keeps two dates for every reactor: the day the first structural concrete was poured, and the day of first connection.[2] India has started 33 power reactors and connected 25. The drawing shows each one as a bar between its two dates.

Every power reactor India has started

From the start of construction to the first connection to the grid, with the years in between. Grouped by design

Built with the United States and Canada

India's 220 MW heavy-water reactor

The same design at 540 MW

Russian design, 1,000 MW

Fast breeder, 500 MW

India's 700 MW heavy-water reactor

Under construction, in yearsTo the date the government expects13 November 2026
A solid bar runs from the first concrete to the first connection. For the eight reactors still being built it stops on 13 November 2026, and the dashed outline runs on to the date the government expects. Dates from the IAEA's Power Reactor Information System; expected dates from the Department of Atomic Energy's replies in Parliament. Download the dates (CSV).

Read the second group. It is one design, a 220 MW heavy-water reactor that India built 14 times. The first four, at Madras and Narora, took 12.6 to 14.2 years each. The next six took 8.0 to 11.1. The last four took 5.0 to 8.7: Kaiga 3, begun in 2002, was on the grid 5.0 years later.[2] Kaiga 4 was finished and then waited for uranium, which India was short of at the time.[6]

The same design at 540 MW went up nearly as fast. Tarapur 4 took 5.2 years and Tarapur 3 took 6.1.

Then India changed designs. Two Russian reactors at Kudankulam took 11.6 and 14.2 years. A new 700 MW heavy-water reactor took 10.1 years at Kakrapar 3, 13.2 at Kakrapar 4 and 13.7 at Rajasthan 7. Rajasthan 8 has been under construction for 15.1 years. The fast breeder at Kalpakkam, begun in 2004, started its first chain reaction on 6 April 2026 and is not yet connected.[10]

The government has given its reasons. Safety reviews after the Fukushima accident changed designs in the middle of construction. The war in Ukraine held up equipment from Russia. A quarry was stopped, contractors ran short of money, and Covid closed sites. The breeder was the first of its kind.[11] In August 2026 the Department of Atomic Energy itself described nuclear power as having a “Project/ Construction period of 10-12 years”.[12]

At that length, most of the target would have to be under construction within a decade. A reactor that takes 12 years must be started by 2035 to count in 2047. One that takes 5.0 can be started as late as 2042.

Time also passes before the first concrete. Two 700 MW reactors at Gorakhpur in Haryana were sanctioned in February 2014. Excavation began in 2018 and found soil that had to be strengthened.[13] On 13 November 2026 the IAEA did not yet list them as under construction.[2] The government expects them about six years after the first concrete, which waits on that ground work.[8]

What the fast builders did

Since the start of 2000, 130 reactors have been connected to a grid somewhere in the world. 58 of them are in China and 14 in India.[2]

Every reactor connected since 2000, by how long it took to build

Years from the first concrete to the first connection, against the year of connection. One dot is one reactor

05101520years under construction200020052010201520202025Kaiga 3 5.0Kudankulam 2 14.2Rajasthan 7 13.7Flamanville 3, France 17.1Olkiluoto 3, Finland 16.6
India: 14 reactors, 9.5 years on averageChina: 58 reactors, 5.9Other countries
Point at a dot to read its name. Nine reactors that took more than 20 years, most of them after work had stopped for years, are left off: Cernavoda 2, Kalinin 4, Rostov 2, Mochovce 3, Mochovce 4, Atucha 2, Angra 2, Bushehr 1, Watts Bar 2. Worked out by us from the IAEA's Power Reactor Information System, read on 13 November 2026.

China's 58 took 5.9 years on average. The fastest took 4.1 and the slowest 9.2. India's 14 took 9.5 years on average. Since 2016 the gap has been wider: 12.8 years for India's 4 reactors and 6.3 for China's 31.

How China did it shows in the list. At Yangjiang it built six reactors of one design and its update, each in 4.1 to 5.8 years, and each was begun before the one ahead of it was connected. Hongyanhe and Fuqing have six reactors each and Tianwan has seven.[2]

China's slow reactors make the same point. Seven took more than eight years. Six of them were the first reactors of two imported designs: an American one at Sanmen and Haiyang, and a French one at Taishan. They took 8.3 to 9.2 years. The seventh was a new kind of gas-cooled reactor. The same American design took 10.1 to 10.3 years at Vogtle in the United States. The same French design took 16.6 years at Olkiluoto in Finland and 17.1 at Flamanville in France.[2]

Cost followed time. By the International Energy Agency's count Vogtle came in at about $14,700 a kilowatt against $5,600 expected at the start, and Flamanville at about $11,000 against $3,200.[14]

South Korea shows it from the other side. It connected eight reactors of its standard 1,000 MW design between 2001 and 2015, and seven of them took 4.1 to 4.8 years. Then it moved to a larger design. The first four at home took 7.2 to 10.5 years.[2] The United Arab Emirates, which had never built a reactor, bought four of that larger design and connected them in 8.0 to 8.6 years each.

The energy agency draws the same lesson from the whole record: reactors arrive on time when a proven design is built again and again by companies that have built it before. Of 52 reactors begun in the world since 2017, 25 are of Chinese design and 23 of Russian.[14]

India's own bars say it too. Its fastest reactors were the eleventh to fourteenth of one design. Every reactor it has connected since 2012 was among the first of a new design, and none took less than ten years.

What the law changed, and what it did not

From 1962 only the central government and its companies could build or run a nuclear power station in India. A new Act received the President's assent on 21 December 2025.[15] It replaces the Atomic Energy Act of 1962 and the liability law of 2010.[9]

The law before and after December 2025
QuestionBeforeUnder the 2025 Act
Who may build, own and run a nuclear power stationThe central government and its companiesAlso any company not incorporated outside India, and joint ventures of government and private companies, under a licence
What the operator pays after an accident, at mostRs 1,500 crore for a power reactorRs 100 crore to Rs 3,000 crore, by the size of the reactor
When the operator can recover that from a supplierIf the contract says so, if the equipment or material supplied was defective, or if someone meant to cause the damageIf the contract says so, or if someone meant to cause the damage
Who pays above the operator's limitThe central governmentThe central government
Who keeps enrichment, reprocessing, high-level waste and heavy waterThe central governmentThe central government
Who sets the price of the electricityThe central governmentThe central government

From the Act, and from PRS Legislative Research's summary of the Bill as introduced.[16][9]

Two changes matter most to anyone thinking of building. The first is that a private Indian company can now hold the licence. The second is the supplier. Under the 2010 law an operator who had paid for an accident could recover the money from the maker of a faulty part. Suppliers named that as their reason for staying out.[5] The new Act removes that ground.[9]

The operator's own limit now depends on the reactor's thermal power, which is about three times its electrical output.[16]

The operator's limit of liability for one accident
Thermal power, MWA reactor of that sizeLimit, Rs crore
More than 3,600A 1,650 MW reactor of the design at Flamanville3,000
1,500 to 3,600India's 700 MW reactor; Kudankulam's 1,000 MW1,500
750 to 1,500India's 220 MW reactor; the fast breeder750
150 to 750A 125 MW small reactor such as China's Linglong 1300
Up to 150The 5 MW gas-cooled reactor India plans100

Limits from the Second Schedule of the Act. The examples are ours, placed by the thermal power the IAEA records for each design. The total for one accident is capped at 300 million special drawing rights, and the central government pays what exceeds the operator's limit.[15]

Three things had not changed by August 2026. The rules that turn the Act into a licensing process were still being drafted, and no private company held a licence.[17] The central government still sets the price of nuclear electricity.[16]

The third is the regulator. The Act gives the Atomic Energy Regulatory Board a footing in law, which it did not have before. But its members are chosen on the advice of a committee formed by the Atomic Energy Commission, and appeals against its orders go to a council chaired by the head of that Commission.[9] The Commission's chairman is the secretary of the Department of Atomic Energy, whose company builds and runs India's reactors. The IAEA's safety standard asks that a regulator be effectively independent, and separate from any body that promotes or operates what it regulates.[18]

The new reactors, and which of them exist

Much of the talk about the target is about reactors that are not built yet: small modular reactors, private reactors beside steel plants, large imported ones. Here is each kind, and where it stood when we read the records.

Each kind of reactor in India's plan
ReactorSize, MWWhere it stands
India's 700 MW heavy-water reactor700Three connected, three under construction, ten more sanctioned and not begun
India's 220 MW heavy-water reactor, offered to industry as the Bharat Small Reactor22014 built, the last begun in 2003. One company has made a proposal for new ones
Russian reactors at Kudankulam1,000Two connected, four under construction
Fast breeder at Kalpakkam500Started up in April 2026, not yet connected. Two more are in early preparation
Bharat Small Modular Reactor220A design. Approved in principle, with a site at Tarapur. Not under construction
SMR-5555A design. Approved in principle, with a site at Tarapur. Not under construction
Gas-cooled reactor to make hydrogen5 thermalA design. Approved in principle, with a site at Visakhapatnam. Not under construction
Large imported reactors at Jaitapur, Kovvada, Mithi Virdi and Haripur1,000 to 1,730Four sites approved in principle for 24 reactors and 29.6 GW. None begun

Counts of reactors from the IAEA. The rest from the Department of Atomic Energy's replies in Parliament.[3][8][19][20][21]

Start with the reactor called the Bharat Small Reactor. It is not a new machine. It is the 220 MW reactor in the second group of the drawing above, offered to companies that would pay for one and take its electricity for their own factories. The request for proposals went out on 31 December 2024 and its deadline was extended to 31 March 2026.[22] By August 2026 one company, Hindalco, had made a proposal.[21]

The small modular reactors are new machines. The government has set aside Rs 20,000 crore for them and aims to have at least five running by 2033.[23][3] Bhabha Atomic Research Centre's own estimate accounts for Rs 14,532 crore of that: Rs 5,960 crore for one 220 MW reactor, Rs 7,000 crore for two of 55 MW, Rs 320 crore for the gas-cooled reactor and the rest for design work and site works. That is four reactors. The 220 MW one is expected to take 60 to 72 months to build from the day its money is approved.[23] In March 2026 the department told the Lok Sabha that no small modular reactor was in operation or under construction in India.[24]

That is true of most of the world. The OECD's Nuclear Energy Agency tracks 127 small modular designs, of which 7 are operating or under construction.[25] The IAEA's list shows what has been built.

Every power reactor of 350 MW or less begun anywhere since 2000
ReactorMWBegunConnectedYears
Kaiga 3India. Heavy water220200220075.0
Chasnupp 2Pakistan. Pressurised water325200520115.2
Chasnupp 3Pakistan. Pressurised water340201120165.4
Chasnupp 4Pakistan. Pressurised water340201120175.5
Rajasthan 6India. Heavy water220200320107.2
Rajasthan 5India. Heavy water220200220097.3
Kaiga 4India. Heavy water220200220118.7
Shidao Bay 1China. Gas-cooled211201220219.0
Akademik Lomonosov 1Russia. Pressurised water352007201912.7
Akademik Lomonosov 2Russia. Pressurised water352007201912.7
Darlington SMR 1Canada. Boiling water3002026Not yet0.6 so far
Linglong 1China. Pressurised water1252021Not yet5.3 so far
Brest-OD-300Russia. Fast reactor3002021Not yet5.4 so far
CAREM25Argentina. Pressurised water292015Not yet11.2 so far

Gross megawatts. Years run from the first concrete to the first connection, or to 13 November 2026. Worked out by us from the IAEA's Power Reactor Information System.

Ten have been connected. Four of them are India's 220 MW reactors and 3 are a Chinese design built in Pakistan. The fastest of all is Kaiga 3. The two reactors of a new kind that were finished, China's gas-cooled reactor at Shidao Bay and Russia's floating pair, took 9.0 and 12.7 years.[2]

The newer projects have not gone to plan. Canada's first, at Darlington, was reported in November 2026 to be late and over budget.[26] The first planned in the United States, in Idaho, was cancelled in November 2023 after its expected price rose from $58 to $89 a megawatt-hour.[27] The International Energy Agency expects electricity from small modular reactors to cost about a fifth more than from large ones even in 2040.[14]

So the small reactor that has actually been built quickly, several times, is one India already owns. Its drawback is size: it takes 415 of them to make 91.2 GW, against 130 of the 700 MW design.

What the electricity would cost

India's existing reactors are cheap to run. Their electricity sold for Rs 3.83 a unit on average in 2023-24.[28] The Central Electricity Authority lists prices from Rs 2.72 a unit at Madras to Rs 3.88 at Kudankulam.[29] In 2025-26 the fleet ran at 79% of its capacity through the year.[30]

New reactors will not match those prices. The authority's indicative figures put a new reactor of India's own design at Rs 15 crore to Rs 21 crore a megawatt to build, and its electricity at Rs 6.41 to Rs 7.77 a unit over its life. For an imported design it gives Rs 24 crore to Rs 30 crore a megawatt, and Rs 6.69 to Rs 7.88 a unit.[29]

Most of that price is the cost of the plant and of the money borrowed to build it. Take the authority's example of a reactor built for Rs 19 crore a megawatt, selling at Rs 7.31 a unit. The return to the owners is Rs 1.99 of that, interest Rs 1.42 and depreciation Rs 0.78. Together they are Rs 4.19, or 57% of the price. Fuel is Rs 1.15.[29] Reactors are financed with 70 parts of debt to 30 of equity.[31]

That is why time matters so much. Interest runs through every year of construction, and nothing is earned until the reactor is connected. The costs of the four most recent projects were all revised upward.[32][31][33]

What four projects were sanctioned at, and what they are now expected to cost
ProjectSanctioned, Rs croreRevised, Rs croreRiseRs crore a MW
Kakrapar 3 and 411,45919,22068%13.7
Rajasthan 7 and 812,32022,92486%16.4
Kudankulam 3 and 439,84968,89373%34.4
Kudankulam 5 and 649,62169,43740%34.7

Rupees of the year each figure was given, not adjusted for inflation. The last column is the revised cost divided by the megawatts, worked out by us.

The fast breeder is now put at Rs 8,181 crore for 500 MW, and is expected to be commissioned by March 2027.[33]

A buyer has other choices. In August 2026 a government auction for round-the-clock electricity from solar, wind and storage, with 90% of the contracted supply to be delivered in the peak hours as well as over the year, closed at Rs 5.25 a unit.[34] A new reactor at the authority's lowest figure is Rs 6.41. The two are not like for like: the reactor's figure is an estimate averaged over its life, and the auction's is a price that bidders have agreed to supply at.

The whole bill is large. At the authority's Rs 15 crore to Rs 21 crore a megawatt, 91.2 GW of India's own design would cost Rs 13.7 lakh crore to Rs 19.2 lakh crore. That sum is ours, and imported reactors would raise it.

What would change the pace

Seven things follow from the record. None of them is a new technology.

  • Build one design many times. In June 2017 the government sanctioned ten 700 MW reactors together, at Rs 1,05,000 crore, so that parts could be ordered in bulk.[20][19] Nine years later two of the ten are under construction. The test is Kaiga 5. The government expects it in June 2031, which would be 5.3 years after its first concrete.[8] The 700 MW design has never been built in less than 10.1 years.
  • Start more at once. If each reactor took six years, adding 4.3 GW a year would mean having 26 GW under construction at all times. India has 6.6 GW. China has 42.1 GW, and the whole world 86.0.[2]
  • Count the years before the concrete. Of the 22,380 MW promised for 2031-32, 8,780 MW is running and 6,600 MW is under construction with a date. The other 7,000 MW is ten 700 MW reactors that the IAEA does not yet list as begun. At Gorakhpur, sanctioned in 2014, the ground is still being prepared.
  • Let the 220 MW reactor out. It is the one design India has built in five years, and the law now lets a company own one. A pair needs about 330 hectares today; the department is studying whether about 90 would do.[21] In its first twenty months the offer drew one proposal.
  • Lower the cost of the money. When 57% of the price is capital, the interest rate and the build time decide whether anyone buys the electricity. The International Energy Agency's report shows how strongly the cost of borrowing moves the price of nuclear electricity.[14]
  • Separate the regulator from the builder. Private owners will be regulated by a board whose members are chosen through the body that runs the state's own programme. The IAEA's standard asks for the two to be apart.[18]
  • Secure the fuel. India's heavy-water reactors under international safeguards run on imported uranium. The department expects them to need about 9,000 tonnes between 2025 and 2033. It bought about 2,000 tonnes from Kazakhstan and Canada in 2020-21 and 600 from Uzbekistan in the two years to 2024-25, and its one long-term contract runs to 2026. India's own ore is poor, which makes it dearer to mine.[35]

The new small designs are not on this list. None has been begun, and the first is expected to take five to six years from the day its money is approved.

What it would take

The target for 2047
100 GW
In operation in August 2026
8.78 GW
To be connected each year from 2027 to 2047
4.3 GW
Connected in India's best ten years, 2016 to 2025
3.1 GW
Under construction at once, if each reactor takes 6 years
26 GW
Under construction in India on 13 November 2026
6.6 GW
Years India's last three reactors took
10.1, 13.2, 13.7 years
Years its fastest took, the eleventh of one design
5.0 years

India has built a reactor in five years. It did it on the eleventh copy of one design. The target needs that speed on every reactor, with about four times as much under construction as India has today, and with owners the law did not allow a year ago.

The nearer date is the one to watch. 22,380 MW by 2031-32 needs Kaiga 5 on the grid in 2031, and it needs ten reactors that have no concrete yet. Even at the 5.3 years promised for Kaiga 5, a reactor begun after the end of 2026 would be connected after March 2032.

What this does not show

  • Nothing on safety or waste. This piece measures how fast reactors are built. It does not judge how safe they are, where spent fuel goes, or whether people near a site agree to it.
  • Not whether 100 GW is the right amount. We have not modelled India's grid in 2047, or what mix of nuclear, solar, wind, storage and coal would serve it at the lowest cost.
  • Build time is two dates. It runs from the first concrete to the first connection. It leaves out the years of approval and site work before, and the months of testing after. It includes any time a project stood still.
  • Capacity at today's ratings. Each reactor is counted at the gross size the IAEA records now, from the year it was connected. Rajasthan 1, which the IAEA lists as suspended, is left out of the capacity line, as it is in the government's count of 24.
  • Six countries. We worked out the most connected in any 21 years for six countries. No other country's whole fleet has reached 91 GW.
  • Indicative costs. The prices for new reactors are the Central Electricity Authority's illustrations at assumed building costs. They are not tariffs anyone has signed. The auction price for renewable power is one auction.
  • A plan we could not read in full. The schedule behind the 100 GW has been described in replies to Parliament. We did not find a published year-by-year plan.
  • The Act as summarised. We read the Act and a summary of the Bill as introduced. The rules under it were not published when we wrote, and they may change what the table says.
  • No person has checked these figures against the sources. The reactor dates were copied from the IAEA's system on 13 November 2026 and checked by sum. Treat the figures with care.

Sources

  1. Ember, Yearly electricity data: nuclear capacity and generation by country and year, and nuclear's share of India's electricity.
  2. International Atomic Energy Agency, Power Reactor Information System, read on 13 November 2026: for every power reactor, its design, its size, the day construction started and the day it was first connected to a grid. Every build time in this piece is worked out by us from those two dates.
  3. Department of Atomic Energy, reply to Rajya Sabha unstarred question 488, 23 July 2026: how the 100 GW is divided, the aim of at least five small modular reactors by 2033, and the approvals each new design has.
  4. Department of Atomic Energy, reply to Lok Sabha starred question 360, 12 August 2026: 24 reactors and 8,780 MW in operation, and 22,380 MW expected by 2031-32.
  5. Observer Research Foundation, Solving India's nuclear liability conundrum, 2015, for the earlier target of 10,000 MW by 2000.
  6. World Nuclear News, “Kaiga 4 connected to grid”, 19 January 2011: the targets of 20,000 MW by 2020 and 63,000 MW by 2032, and the shortage of uranium that held up Kaiga 4.
  7. Department of Atomic Energy, reply to Rajya Sabha unstarred question 803, 9 February 2023.
  8. Department of Atomic Energy, reply to Lok Sabha unstarred question 1705, 29 July 2026: the expected date of commissioning of each reactor under construction, and the state of work at Gorakhpur.
  9. PRS Legislative Research, summary of the Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India Bill, 2025, 17 December 2025. It describes the Bill as introduced.
  10. Department of Atomic Energy, “Prototype Fast Breeder Reactor at Kalpakkam, Tamil Nadu attains first criticality”, 7 April 2026.
  11. Department of Atomic Energy, reply in Parliament of 3 December 2025, Press Information Bureau: the reasons given for the delay of each reactor under construction.
  12. Department of Atomic Energy, reply to Lok Sabha unstarred question 2881, 5 August 2026.
  13. Department of Atomic Energy, reply to Lok Sabha starred question 259, 6 August 2025, on the Gorakhpur project in Haryana.
  14. International Energy Agency, The Path to a New Era for Nuclear Energy, January 2025: what recent reactors cost against their first estimates, whose designs are being built, and what the cost of borrowing does to the price of nuclear electricity.
  15. Department of Atomic Energy, reply in Parliament of 1 April 2026, Press Information Bureau: the date of assent to the new Act and its limits on liability.
  16. The Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India Act, 2025, as published in the Gazette of India and hosted by PRS Legislative Research: sections 3 and 11 to 18, and the Second Schedule.
  17. Department of Atomic Energy, reply to Lok Sabha unstarred question 4075, 12 August 2026, on the rules under the new Act.
  18. International Atomic Energy Agency, Governmental, Legal and Regulatory Framework for Safety, General Safety Requirements Part 1 (Rev. 1), Requirement 4, on the independence of the regulatory body.
  19. Department of Atomic Energy, reply to Lok Sabha unstarred question 1536, 27 November 2019: the ten 700 MW reactors sanctioned together, and the sites approved in principle for imported reactors.
  20. Department of Atomic Energy, reply in Parliament on the sanction of June 2017 and its cost.
  21. Department of Atomic Energy, reply to Rajya Sabha unstarred question 2087, 6 August 2026, on Bharat Small Reactors: the one proposal received, and the land a pair of reactors needs.
  22. Department of Atomic Energy, reply to Rajya Sabha starred question 223, 12 March 2026: the dates of the request for proposals.
  23. Department of Atomic Energy, reply to Lok Sabha unstarred question 3062, 11 March 2026: the Rs 20,000 crore set aside for small modular reactors and how Bhabha Atomic Research Centre expects to use it.
  24. Department of Atomic Energy, reply to Lok Sabha starred question 468, 25 March 2026.
  25. OECD Nuclear Energy Agency, The NEA Small Modular Reactor Dashboard, third edition, 2025.
  26. Canary Media, report on the small modular reactor at Darlington, Canada, 11 November 2026.
  27. Utility Dive, report on the end of the small modular reactor project in Idaho, 9 November 2023.
  28. Department of Atomic Energy, reply to Lok Sabha starred question 226, 11 December 2024: the average price of nuclear electricity in 2023-24.
  29. Central Electricity Authority, Nuclear tariff norms and tariff, a presentation written after the Act and not dated: prices at existing stations, and indicative prices for new reactors at a range of building costs.
  30. Department of Atomic Energy, reply to Rajya Sabha unstarred question 1281, 30 July 2026: nuclear generation and plant load factor in 2025-26.
  31. Department of Atomic Energy, reply to Lok Sabha unstarred question 2590, 4 December 2019: how reactors are financed, and the sanctioned cost of the Kudankulam reactors.
  32. Department of Atomic Energy, reply to Rajya Sabha unstarred question 3205, 31 March 2022: the sanctioned cost of each project.
  33. Department of Atomic Energy, reply in Parliament of 29 July 2026, Press Information Bureau: the revised cost of each project, and the cost and expected date of the fast breeder.
  34. pv magazine India, “SECI's 1 GW FDRE RTC power tender discovers INR 5.25/kWh tariff”, 7 August 2026.
  35. Department of Atomic Energy, reply to Lok Sabha unstarred question 4230, 26 March 2025, on uranium imports.

Grid Search is the energy project of Seed 42 Labs. Our subject is electricity: what generates it, in India and the rest of the world.